Actual Situation

Ansasol Logo

Register

of the development process

Plano de los módulosThe already signed land lease agreement is one of the steps required during the approval process. The connection to a transformer station that is assigned by the Red Eléctrica Española (operator of the Spanish grid) has to be assured as well.

The license for the construction of the plant (Autorización Administrativa) has to be applied for at the Ministry of Industry in Madrid. This central Ministry will coordinate with any other administration involved during the permission process.

The time frame for the assignation of all necessary permissions is about 15 to 18 months. In order to submit the application for the project at the Ministry it is necessary to present the technical details of the access to the transformer station and an environmental study on the impact caused by the construction. Besides an aval over 2% of the amount to be invested needs to be provide. Aditionally you haveto realize various enquirys with the town hall, the andalusian administration etc. Right now we closing the last details of a strategy agreement.

Right now the project got his connection point with Red Electrica. The land leases are signed, aval is deposited and we applied at the industry ministry (MINETUR) the declaration of public interest of the project the overall permission (Autorización Administrativa) and the environmental studies.

Puerto Real, Cádiz

Ansasol Logo

Our Address:

Urb. Alvarito Playa II
Bloque 4 - 1-14
c/ Andasol, s/n
29604 Marbella (Málaga)
Spain

Contact Us

This email address is being protected from spambots. You need JavaScript enabled to view it.

Phone: +34 952 765 666

Fax: +34 952 765 627

S5 Box

Login

Register